Eton Irrigation will be chemically treating for aquatic weed control in the channel system during the following period when water WILL NOT be available. 

11th January 2021 until 16th January 2021

Customers should ensure that they have adequate storage for this period.

Customers are requested to cease pumping at the times stipulated for their respective areas.  This will prevent pipelines being drained and reduce the possibility of having to refill these lines.  Details of the stipulated times shown on below.  The planned program for the year are shown below and are on the Eton Irrigation website.

Should you be unsure as to whether this will affect you, please do not hesitate to call John Badger at Eton Irrigation on 0417 798 913 for clarification.  Please have all your offtake numbers available.

Closedown Schedule for Period Monday 11th  January to Saturday 16th January 2021

Planned Resumption of Supply for Agricultural Customers
Reticulation AreaStop TimeStop DateRestart TimeRestart Date
OMC (1-13)7:00Mon 11th Jan7:00Thu 14th Jan 
Brightley (14-54A) Abingdon (501-515)7:00Mon 11th Jan17:00Thu 14th Jan 
OMC (67-95)17:00Mon 11th Jan7:00  Fri 15th Jan
Vic Plains (401 -482) Oakenden Relift(127-137C))7:00Mon 11th Jan17:00  Fri 15th Jan
OMC (96-140)17:00Mon 11th Jan17:00  Fri 15th Jan
OMC (140A – 161)                         7:00Tue 12th Jan17:00  Sat 16th Jan
OMC (156A – 165) Mt.Alice (301 – 385)  7:00Mon 11th Jan17:00    Sat 16th Jan
OMC (165A – 181) Marwood (183 – 260) & (390A – 398) Munbura (261 – 299A)17:00Mon 11th Jan7:00      Sat 16th Jan
  • Mt Alice Reticulation is off line for a longer period, as the storage has to be treated prior to dewatering the channel. The channel must then be refilled in order to re-instate the pump station.

Planned Acrolein Injection Dates  2021Injection period duration
  11th – 16th January 20216 days
  15th – 20th February 20216 days
  5th – 10th April 20216 days
  10th – 15th May 20216 days
  20th – 25th September 20216 days
  1st – 6th November 20216 days