Interruption to Supply
Eton Irrigation Water Supply Scheme
Eton Irrigation will be chemically treating for aquatic weed control in the channel system during the following period when water WILL NOT be available.
21st September 2020 until 26th September 2020
Customers should ensure that they have adequate storage for this period.
Customers are requested to cease pumping at the times stipulated for their respective areas. This will prevent pipelines being drained and reduce the possibility of having to refill these lines. Details of the stipulated times shown on below. The planned program for the year are shown below and are on the Eton Irrigation website.
Should you be unsure as to whether this will affect you, please do not hesitate to call John Badger at Eton Irrigation on 0417 798 913 for clarification. Please have all your offtake numbers available.
Closedown Schedule for Period Monday 21st September to Saturday 26th September 2020
Planned Resumption of Supply for Agricultural Customers | ||||
Reticulation Area | Stop Time | Stop Date | Restart Time | Restart Date |
OMC (1-13) | 7:00 | Mon 21st Sept | 7:00 | Thu 24th Sept |
Brightley (14-54A) Abingdon (501-515) | 7:00 | Mon 21st Sept | 17:00 | Thu 24th Sept |
OMC (67-95) | 17:00 | Mon 21st Sept | 7:00 | Fri 25th Sept |
Vic Plains (401 -482) Oakenden Relift(127-137C)) | 7:00 | Mon 21st Sept | 17:00 | Fri 25th Sept |
OMC (96-140) | 17:00 | Mon 21st Sept | 17:00 | Fri 25th Sept |
OMC (140A – 161) | 07:00 | Tue 22nd Sept | 17:00 | Sat 26th Sept |
OMC (156A – 165) Mt.Alice (301 – 385) | 7:00 | Mon 21st Sept | 17:00 | Sat 26th Sept |
OMC (165A – 181) Marwood (183 – 260) & (390A – 398) Munbura (261 – 299A) | 17:00 | Mon 21st Sept | 7:00 | Sat 26th Sept |
- Mt Alice Reticulation is off line for a longer period, as the storage has to be treated prior to dewatering the channel. The channel must then be refilled in order to re-instate the pump station.
Planned Acrolein Injection Dates 2020/21 | Injection period duration |
21st – 26th September 2020 | 6 days |
2nd – 7th November 2020 | 6 days |
7th – 12th December 2020 | 6 days |
11th – 16th January 2021 | 6 days |
15th – 20th February 2021 | 6 days |
5th – 10th April 2021 | 6 days |
General Manager
M:- 0427 277 906
E:- austin.evans@etonirrigation.com.au