Interruption to Supply Eton Irrigation Water Supply Scheme Eton Irrigation will be chemically treating for aquatic weed control in the channel system during the following period when water WILL NOT be available. 

Planned Acrolein Injection Dates  2020/21Injection period duration
  7th – 12th December 20206 days
  11th – 16th January 20216 days
  15th – 20th February 20216 days
  5th – 10th April 20216 days
  10th – 15th May 20216 days
  20th – 25th September6 days

Closedown Schedule for Period Monday 7th  December to Saturday 12th December 2020

Planned Resumption of Supply for Agricultural Customers
Reticulation AreaStop TimeStop DateRestart TimeRestart Date
OMC (1-13)7:00Mon 7th Dec           7:00Thu 10th Dec 
Brightley (14-54A) Abingdon (501-515)7:00Mon 7th Dec17:00Thu 10th Dec 
OMC (67-95)17:00Mon 7th Dec7:00    Fri 11th Dec
Vic Plains (401 -482) Oakenden Relift(127-137C))7:00Mon 7th Dec17:00  Fri 11th Dec
OMC (96-140)17:00Mon 7th Dec17:00  Fri 11th Dec
OMC (140A – 161)                         07:00Tue 8th Dec17:00  Sat 12th Dec
OMC (156A – 165) Mt.Alice (301 – 385)  7:00Mon 7th Dec17:00    Sat 12th Dec
OMC (165A – 181) Marwood (183 – 260) & (390A – 398) Munbura (261 – 299A)17:00Mon 7th Dec7:00      Sat 12th Dec
  • Mt Alice Reticulation is off line for a longer period, as the storage has to be treated prior to dewatering the channel. The channel must then be refilled in order to re-instate the pump station.