Shutdown Works Report

13 Oct, 2026

1.1        Shutdown Works

Good weather over the shutdown period allowed a large number of the planned works to be completed.

4 casuals (contractor Wayne Coyne, customer Hayden Williams, externals Mitch Mallyon and Lynton Choppy) were employed to assist with the works – note that Wayne and Mitch did 3 weeks between them (like job sharing).  We think it worked well and plan to do it again next year.

A map showing the location of all the works is shown below.  The map has 3 icons in the Legend:

  • a black cross for completed works that were in the original shutdown works plan
  • a red cross for completed new works that were not in the original shutdown works plan
  • a yellow dot for all the works. If there is no cross (red or black) that item was planned but not completed

A summary of the budget and spending in each category is shown in the table below.

 

The following sections discuss the works by each category.

 

Desilting                                              Budget: $30,000                Actuals: $20,632.90 (so far)

The last two sections of the channel were desilted during the shutdown.  The removed silt has dried out quickly due to the dry weather.  The spreading and levelling of the silt is being done at the moment and may be finished this week.  Once completed and the final invoices received, we can finalise this category.

Regulator Gate Valves                   Budget: $18,000                Actuals: $17,565.10

The valves for the float tanks of these regulator gates were purchased last year.  An easy and safe way to complete this work was developed.  Two of the valves were cleaned and reinstalled, whilst the third was so deteriorated that it was replaced.  All 3 gates were stripped and rebalanced.

 

Meter Outlets                                   Budget: $135,000             Actuals: $118,041.17

The budget for meter outlets was set at 9 outlets @$15,000 each for a total of $135,000.  In the shutdown works plan, 12 outlets were identified as a pool of possible outlets that could be done.

All 12 of those were completed (3 prior to the shutdown and 9 during the shutdown) and 2 extra outlets were connected to the system as far as the isolation valves during the shutdown.  One of those 2 has since been completed, with the other one nearing completion.

The average cost of the 13 completed outlets was $8,538.73, well below the estimated $15,000 each.  With the benefit of hindsight, the budget figure was for a complete installation, whereas all but 2 of the 14 were only upgrades.  This means that we are on track to complete the 14 outlets within the budget set for 9 outlets.

Details of the work done at each site is shown on the Reconciliation tab of the spreadsheet.

 

Isolation Valves                                                Budget: $52,000                Actuals: $42,477.48

A range of isolation valves were in the shutdown works plan for replacement or repair at a surge tank, a pump station, pipelines and meter outlets.  The prices of each varied with the size and difficulty of the job.  The most expensive of these was the isolation valve at the OMC Lateral 5 offtake across the road from the Oakenden School.  We had postponed this last year when the shoring that was arranged was determined to be inadequate.

We had organised a contractor this year with larger shoring to complete the work.  Just prior to the shutdown period, that contractor bailed on us.  That left us with no time to organise a replacement.

The decision was made to use that $20,000 and $2,000 from a smaller one not done, towards replacing the isolation valves at 7 meter outlets that weren’t in the shutdown works plan.

Air Valves/Risers                             Budget: $85,000                Actuals: $34,724.58

A range of air valves & risers were in the shutdown works plan for replacement.  This included a couple of group items – $20K for Air Vent posts on OMC laterals and $30K for converting 9 Air Vents to Air Valves at Munburra – that never happened.

Similarly to the isolation valves, the decision was made to use that money towards replacing 12 air valves and risers on the Mt Alice pipeline.

 

Earthworks                                         Budget: $26,000                Actuals:

$23,322.50

The earthworks planned for shutdown were a large repair near the Marwood OT and two small repairs near the top of the OMC.  Once dewatering was completed, the two small repairs were assessed and determined to be monitored instead.

The large repair near the Marwood OT was a section of channel that had weeped through the bank for many years.  It was excavated and refilled with compacted clay.  Once we refilled the channel, a very small amount of seepage was still occurring, but the works seem to have stopped most of it.  A granular product was suggested to EICL that might stop that last bit of seepage.  We will make some inquiries and may get some of it to try.  The water flow has to be reasonably static for the product to work.

 

Screens                                                Budget: $20,000                Actuals: $27,175.50

The 3 screens planned for in the shutdown were removed, repaired, blasted, recoated & reinstalled.  We weren’t sure if this could all be done within the allowable time, but it was successful.

Reseal, Scour & Concrete             Budget: $45,000                Actuals: $33,088.90

The scour and concrete categories were combined as they were mostly resealing of both.  The one exception was the new scour structure to supply drained water to the Racecourse Projects storage, which did not go ahead as the GM is struggling to complete a design that will come in under $20K.

The plastering job on the Break Pressure Structure for $6K was assessed as not being needed once the water was taken off.

Nathan Hollis worked in with Steve Probyn to complete these works.  They used a range of new grouts and sealants to stop the leaks.  The work was progressing so well that 5 extra sites were treated.  It is expected that this sealing work should significantly extend the life of these structures.

Offtake Gate                                      Budget: $32,000                Actuals: $26,880

The offtake gate at the Victoria Plains diversion channel was deemed to be in need of replacement.  The gate was ordered from AWMA in the usual timeframes.  What we didn’t count on, was that AWMA had changed their process and added a couple of extra steps.  This meant that the gate did not arrive in time for the shutdown.  The plan is to install it next year.

Pump Rails                                         Budget: $8,000                  Actuals: $0

The pump rails that hold the submersible pumps at the Abingdon pump station are due for an inspection below the water.  Sunwater used to do this with divers.  The budget figure was based on that.

Prior to the shutdown, a clamp and poles were made for the underwater drone so that we have better control of it.  With that we expect to be able to complete the inspection without using divers, during the irrigation season.

 

Extra Work Done                             Budget: $0                          Actuals: $31,460.45

4 extra jobs were done during the shutdown that were not accounted for in any of the above budget items:

  • One of the reflux valves at the Oakenden relift pump had been leaking. With the water off, the opportunity was taken to repair it.  Cost: $7,851.64
  • The mechanical seals on pump 1 at the Brightley 1 pump station have worn and no longer functioning correctly. During the shutdown the pump was removed and the pipework blanked off.  The seals are being refurbished and once completed, will be reinstalled at the first opportunity.  Cost so far: $3,095.70

  • The air intake line was repaired at MO477. Cost: $1067.43

 

  • A leak was noticed at the first drainage over pass on the OMC. This is close to the site of the former pipe meter that has not worked for years.  It was thought that the leak might have been related to this meter, but once excavated, it was found to be a rubber ring failure.  This is a big pipe (1 of 2) and the excavation had to be quite large to access the pipe.  With most of the meter hardware already exposed, it was decided to clean up the concrete tank meter hut and the pad it sat on, whilst the excavator was there.  This should allow any drainage to flow better through that area.  Cost: $19,445.68